Read a second time, on March 17, 2025.
2024–2025 Session
Senate Resolution 125
Urges states in PJM Interconnection region to require data centers to obtain electricity from new zero- or low-emission sources of energy.
Sponsors
Who carried the bill in each chamber, and who signed on. Each name leads to the member's page.
In the Senate
Sponsor from Feb 13
Chief co-sponsor from Feb 20
Votes
Yeas to nays, as the Legislature recorded them. Committee votes are set in.
Do pass · Mar 17
Text
Each version as the Legislature printed it.
l9n doesn't hold this bill's text yet.
What happened
In l9n's words, one line for each step. Every action as the Legislature published it is below.
In the Senate Feb 20 – Mar 17
- Feb 20Introduced in the Senate and sent to Environment and Energy
- Mar 17Environment and Energy recommended it
- Read a second time
All 2 actions, as published
- Feb 20INT 1RS REF SENSenate
- Mar 17REP 2RSSenate