Senate Bill 2732

Extends deadlines, under certain circumstances, for completion and commercial operation of certain solar electric power generation facilities.

Did not become law. It stopped in the Senate on June 30, 2023. The 2022–2023 session has ended.

Sponsors

Who carried the bill in each chamber, and who signed on. Each name leads to the member's page.

In the Senate

4 co-sponsors

Andrew Zwicker, Jean Stanfield, Patrick J. Diegnan Jr., Linda R. Greenstein

Its course

May 26, 2022 to June 30, 2023, on one scale. In the top row each mark is a day something happened; taller marks are busier days.

Each committee stop sits inside its chamber.

Every action7 actions on 6 days

In the SenateMay 26 to Jun 30 · stopped400 days

Environment and EnergyMay 26 to Jun 914 days

Budget and AppropriationsJun 27 to Jun 270 days

Amendments

Each amendment offered, and what became of it.

  • Senate committee amendmentAdopted

    Adopted Jun 9

  • Senate floor amendmentAdopted

    Adopted Jun 20, 2023

  • Senate floor amendmentAdopted

    Adopted Jun 26, 2023

  • Senate committee amendmentAdopted

    Adopted Jun 27, 2023

Text

Each version as the Legislature printed it.

l9n doesn't hold this bill's text yet.

What happened

In l9n's words, one line for each step. Every action as the Legislature published it is below.

In the Senate May 26 – Jun 30, 2023

  1. Introduced in the Senate and sent to Environment and Energy
  2. Environment and Energy recommended it as amended
  3. Read a second time
  4. Amended on the floor and read a second time
  5. Amended on the floor and read a second time
  6. Sent to Budget and Appropriations
  7. Budget and Appropriations recommended it as amended
  8. Read a second time
  9. Carried on in A4089